Construction continues replacing the left spillway in the dam at Leonard’s Mill. The footings were poured earlier this week (see the first video). The construction crew worked into the night on Thursday placing rebar, forms, and pouring the concrete for the sides and top of the spillway (see the second video). The photos are from Tuesday, Thursday, and Saturday. The last few photographs are of the construction crew recreating the dam wall on either side of the spillway and backfilling the area between the spillway and where stone was removed to rebuild that section of the dam. There is still lots of water coming down Blackman Stream from Chemo Pond and through the center spillway, fishway and Mill Pond spillway.